Production

Start a production run

Plan and start a production run.

  • 4 min
  • Intermediate
  • Updated on October 17, 2026

Step by step

  1. 1

    Open a new run

    Go to the Workshop, then “Production”, and click + New run

  2. 2

    Choose products and quantities

    Choose the products to make and their quantities (“Add a line” to add more), with a “Due date (optional)” and a note if needed.

  3. 3

    Check what the run consumes

    “See what it consumes” lists the materials needed and shows what will be missing, without blocking anything.

  4. 4

    Start the run

    Materials are taken out of stock as soon as the run starts; finished products will enter stock when it is closed. Click Start production

  5. 5

    Close and deliver

    At the end, “Close the run”: enter what actually came out of the workshop, product by product. Successful quantities enter stock, and the material of units not produced is returned.

What you can do

  • “Duplicate a run” reuses a past run to start the same production again.
  • “Cancel this run” returns exactly what was taken: the materials consumed and the stock produced.
  • A missing material does not block: the stock goes negative. Only a product with no recipe or gift box attached prevents production.